Hazen Municipal Airport – Runway & Apron Rehabilitation (Hazen, Arkansas)
In September 2026, we completed the rehabilitation of Runway 18-36 and the aircraft apron at Hazen Municipal Airport for the City of Hazen, a contract we won through competitive public bidding. The work included more than 100,000 linear feet of crack sealing, removal of old markings and rubber buildup, and a coal tar seal coat over more than 65,000 square yards of pavement. We then applied new pavement markings and finished with runway friction testing. The biggest challenge was finishing everything within 30 days while the runway was closed. The new seal coat also had to cure for 30 days before the final markings could go down, so we applied temporary markings first. Close coordination with the engineer and airport management let us return the airport to full service on schedule.